Frederick Douglass Boulevard Community Garden Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Frederick Douglass Boulevard Community Garden with new pavements, plantings, and sidewalks.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: August 2019

Procurement

Start Date: March 2019
Projected Completion Date: August 2019
Completion Date: August 2019

Construction

Start Date: August 2021
Projected Completion Date: October 2021
Completion Date: October 2021

Understand how we build parks.

Funding

Total Funding: $107,000
Funding Source: Mayoral

Location

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024