Maurice A. Fitzgerald Playground Ballfield Lighting Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the ballfield lighting at Maurice A. Fitzgerald Playground with energy-efficient LED fixtures.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2021
Projected Completion Date: June 2022
Completion Date: December 2022

Procurement

Start Date: December 2021
Projected Completion Date: May 2022
Completion Date: October 2022

Construction

Start Date: October 2023
Projected Completion Date: December 2023
Completion Date: December 2023

Understand how we build parks.

Funding

Total Funding: $250,000
Funding Source: Mayoral

Location

Maurice A FitzGerald Playground, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024