Project Timeline
Design
Assigned & Start Date: October 2021
Projected Completion Date:
June 2022
Completion Date:
November 2022
Procurement
Start Date: December 2021
Projected Completion Date:
May 2022
Completion
Date:
October 2022
Construction
Start Date: November 2023
Projected Completion Date:
March 2024
Completion Date: December 2023
Understand how we build parks.