Forest Park Paths and Sidewalk Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct pathways and sidewalks at Forest Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2022
Projected Completion Date:
June 2023
Completion Date:
March 2023
Procurement
Start Date: January 2023
Projected Completion Date:
July 2023
Completion
Date:
February 2023
Construction
Start Date: December 2023
Projected Completion Date:
December 2024
Understand how we build parks.
Funding
Funding Source: City Council
Location
Forest Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024