Rev. J. Polite Playground Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf field at Rev. J. Polite Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2021
Projected Completion Date:
August 2022
Completion Date:
April 2022
Procurement
Start Date: September 2021
Projected Completion Date:
February 2022
Completion
Date:
April 2022
Construction
Start Date: June 2022
Projected Completion Date:
August 2022
Completion Date: August 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Rev J Polite Playground, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025