Columbus Park Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf field at Columbus Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2021
Projected Completion Date: August 2022
Completion Date: April 2022

Procurement

Start Date: September 2021
Projected Completion Date: February 2022
Completion Date: April 2022

Construction

Start Date: June 2022
Projected Completion Date: July 2022
Completion Date: July 2022

Understand how we build parks.

Funding

Total Funding: $552,000
Funding Source: Mayoral

Location

Columbus Park, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025