Bushwick Inlet Park Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf field at Bushwick Inlet Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2021
Projected Completion Date:
April 2022
Completion Date:
April 2022
Procurement
Start Date: September 2021
Projected Completion Date:
February 2022
Completion
Date:
April 2022
Construction
Start Date: May 2022
Projected Completion Date:
August 2022
Completion Date: July 2022
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Bushwick Inlet Park, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024