Bushwick Inlet Park Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf field at Bushwick Inlet Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2021
Projected Completion Date: April 2022
Completion Date: April 2022

Procurement

Start Date: September 2021
Projected Completion Date: February 2022
Completion Date: April 2022

Construction

Start Date: May 2022
Projected Completion Date: August 2022
Completion Date: July 2022

Understand how we build parks.

Funding

Total Funding: $3,193,000