Howard Park Pool Deck Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pool deck at Howard Park Pool.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2022
Projected Completion Date: September 2022
Completion Date: September 2022

Procurement

Start Date: May 2022
Projected Completion Date: October 2022
Completion Date: August 2022

Construction

Start Date: October 2022
Projected Completion Date: June 2023
Completion Date: February 2023

Understand how we build parks.

Funding

Total Funding: $1,190,000
Funding Source: Mayoral

Location

Howard Playground, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024