Inwood Hill Park Paths Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct paths in Inwood Hill Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2021
Projected Completion Date: September 2022
Completion Date: April 2022

Procurement

Start Date: December 2021
Projected Completion Date: May 2022
Completion Date: March 2022

Construction

Start Date: June 2022
Projected Completion Date: September 2022
Completion Date: August 2022

Understand how we build parks.

Funding

Total Funding: $700,000
Funding Source: Mayoral