Juniper Valley Park Water Service Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will provide water service to the spray shower at Juniper Valley Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2021
Projected Completion Date: May 2022
Completion Date: September 2021

Procurement

Start Date: July 2021
Projected Completion Date: December 2021
Completion Date: March 2022

Construction

Start Date: April 2022
Projected Completion Date: September 2022
Completion Date: September 2022

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Juniper Valley Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024