Juniper Valley Park Water Service Installation
-
100% complete
-
100% complete
-
100% complete
This project will provide water service to the spray shower at Juniper Valley Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2021
Projected Completion Date:
May 2022
Completion Date:
September 2021
Procurement
Start Date: July 2021
Projected Completion Date:
December 2021
Completion
Date:
March 2022
Construction
Start Date: April 2022
Projected Completion Date:
September 2022
Completion Date: September 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Juniper Valley Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024