Claremont Park Retaining Wall Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct a 115-foot section of damaged stone block retaining wall along Clay Avenue between Claremont Parkway and East 170th Street.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
January 2023
Completion Date:
January 2023
Procurement
Start Date: March 2023
Projected Completion Date:
August 2023
Completion
Date:
October 2021
Construction
Start Date: December 2022
Projected Completion Date:
September 2023
Completion Date: September 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Claremont Park, Bronx
Project Staff
Project Liaison: Contact Us
Contact NYC Parks
about this project
Last updated: 01/17/2025