Claremont Park Retaining Wall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct a 115-foot section of damaged stone block retaining wall along Clay Avenue between Claremont Parkway and East 170th Street.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2022
Projected Completion Date: January 2023
Completion Date: January 2023

Procurement

Start Date: March 2023
Projected Completion Date: August 2023
Completion Date: October 2021

Construction

Start Date: December 2022
Projected Completion Date: September 2023
Completion Date: September 2023

Understand how we build parks.

Funding

Total Funding: $522,000
Funding Source: Mayoral

Location

Claremont Park, Bronx

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 10/11/2024