Colucci Playground Seating Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct new fencing, gates, planting beds, benches, pavements, and a water supply system in Colucci Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2014
Projected Completion Date:
June 2015
Completion Date:
July 2015
Procurement
Start Date: July 2015
Projected Completion Date:
April 2016
Completion
Date:
July 2016
Construction
Start Date: August 2016
Projected Completion Date:
August 2017
Completion Date: August 2017
Understand how we build parks.
Funding
Funding Source: City Council
Location
Colucci Playground, Bronx
Wilkinson Avenue between Hutchinson River Parkway East and Mayflower Avenue
Community Board: 10
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024