Brower Park Pathway Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct a portion of the pathways in Brower Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2021
Projected Completion Date:
November 2021
Completion Date:
September 2021
Procurement
Start Date: July 2021
Projected Completion Date:
December 2021
Completion
Date:
September 2021
Construction
Start Date: October 2021
Projected Completion Date:
February 2022
Completion Date: November 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Brower Park, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025