Gertrude Ederle Recreation Center Fitness Room Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the fitness room at Gertrude Ederle Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2022
Projected Completion Date: September 2022
Completion Date: January 2022

Procurement

Start Date: January 2022
Projected Completion Date: June 2022
Completion Date: June 2022

Construction

Start Date: November 2023
Projected Completion Date: December 2024

Understand how we build parks.

Funding

Total Funding: $363,000
Funding Source: City Council

Location

Gertrude Ederle Recreation Center, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024