Asser Levy Recreation Center Fitness Room Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the fitness room at Asser Levy Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
September 2022
Completion Date:
January 2022
Procurement
Start Date: January 2022
Projected Completion Date:
June 2022
Completion
Date:
June 2022
Construction
Start Date: March 2023
Projected Completion Date:
December 2023
Completion Date: June 2023