Asser Levy Recreation Center Fitness Room Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the fitness room at Asser Levy Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2022
Projected Completion Date: September 2022
Completion Date: January 2022

Procurement

Start Date: January 2022
Projected Completion Date: June 2022
Completion Date: June 2022

Construction

Start Date: March 2023
Projected Completion Date: December 2023
Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $689,000
Funding Sources:
  • Mayoral
  • City Council

Location

Asser Levy Playground, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024