Van Cortlandt Park Shandler Recreation Area Paths Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct paths at Shandler Recreation Area in Van Cortlandt Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2022
Projected Completion Date: May 2022
Completion Date: June 2022

Procurement

Start Date: March 2022
Projected Completion Date: August 2022
Completion Date: March 2022

Construction

Start Date: February 2023
Projected Completion Date: November 2023
Completion Date: August 2023

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Source: Mayoral

Location

Van Cortlandt Park, Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024