Raymond Bush Playground Drainage Line Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the main water and sewer drainage line at Raymond Bush Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2021
Projected Completion Date: March 2022
Completion Date: February 2022

Procurement

Start Date: August 2021
Projected Completion Date: January 2022
Completion Date: January 2022

Construction

Start Date: May 2022
Projected Completion Date: August 2022
Completion Date: September 2022

Understand how we build parks.

Funding

Total Funding: $180,000
Funding Source: City Council

Location

Raymond Bush Playground, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025