Raymond Bush Playground Drainage Line Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the main water and sewer drainage line at Raymond Bush Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2021
Projected Completion Date:
March 2022
Completion Date:
February 2022
Procurement
Start Date: August 2021
Projected Completion Date:
January 2022
Completion
Date:
January 2022
Construction
Start Date: May 2022
Projected Completion Date:
August 2022
Completion Date: September 2022