Astoria Park Field House Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roof of the field house in Astoria Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2021
Projected Completion Date:
April 2022
Completion Date:
August 2021
Procurement
Start Date: April 2021
Projected Completion Date:
September 2021
Completion
Date:
June 2021
Construction
Start Date: July 2021
Projected Completion Date:
January 2022
Completion Date: November 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Astoria Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks