Willowbrook Park Public Restroom Building Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof of the public restroom building in Willowbrook Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2021
Projected Completion Date: April 2022
Completion Date: August 2021

Procurement

Start Date: April 2021
Projected Completion Date: September 2021
Completion Date: June 2021

Construction

Start Date: July 2022
Projected Completion Date: November 2022
Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $279,000
Funding Source: Mayoral

Location

Willowbrook Park, Staten Island

 

Project Staff

Project Liaison: Cristin Leoutsakos