Alfred E. Smith Recreation Center Fitness Room Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the fitness room in Alfred E. Smith Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2022
Projected Completion Date: September 2022
Completion Date: January 2022

Procurement

Start Date: January 2022
Projected Completion Date: June 2022
Completion Date: June 2022

Construction

Start Date: September 2023
Projected Completion Date: February 2024
Completion Date: December 2023

Understand how we build parks.

Funding

Total Funding: $571,000
Funding Source: Mayoral

Location

Alfred E. Smith Playground, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024