Parade Ground Parks Enforcement Facility Windows, Storefront and HVAC Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the windows, storefront and HVAC at the Parade Grounds Park Enforcement Facility.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2022
Projected Completion Date: October 2022
Completion Date: April 2022

Procurement

Start Date: April 2022
Projected Completion Date: September 2022
Completion Date: May 2022

Construction

Start Date: November 2023
Projected Completion Date: December 2024
Completion Date: May 2024

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Source: Mayoral

Location

Parade Ground, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project