Vic Hanson Field House Telecommunication Lines Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the telecommunication lines to Vic Hanson Field House in Rochdale Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: May 2021
Completion Date: September 2021

Procurement

Start Date: April 2021
Projected Completion Date: September 2021
Completion Date: June 2021

Construction

Start Date: February 2022
Projected Completion Date: May 2022
Completion Date: March 2022

Understand how we build parks.

Funding

Total Funding: $180,000
Funding Source: Mayoral

Location

Rochdale Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos