Vic Hanson Field House Telecommunication Lines Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the telecommunication lines to Vic Hanson Field House in Rochdale Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
May 2021
Completion Date:
September 2021
Procurement
Start Date: April 2021
Projected Completion Date:
September 2021
Completion
Date:
June 2021
Construction
Start Date: February 2022
Projected Completion Date:
May 2022
Completion Date: March 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Rochdale Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024