Sunset Park Recreation Center Telecommunication Lines Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the telecommunication lines to Sunset Park Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2020
Projected Completion Date: May 2021
Completion Date: September 2021

Procurement

Start Date: March 2021
Projected Completion Date: August 2021
Completion Date: June 2021

Construction

Start Date: November 2021
Projected Completion Date: February 2022
Completion Date: March 2022

Understand how we build parks.

Funding

Total Funding: $128,000
Funding Source: Mayoral