St. Nicholas Park Rockface Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the rockface along St. Nicholas Avenue between West 138th Street and West 139th Street in St. Nicholas Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: December 2020
Completion Date: March 2021

Procurement

Start Date: December 2020
Projected Completion Date: May 2021
Completion Date: October 2021

Construction

Start Date: January 2022
Projected Completion Date: April 2022
Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $966,000
Funding Source: Mayoral

Location

St. Nicholas Park, Manhattan

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 10/11/2024