Fort Tryon Park Retaining Wall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the retaining wall along Bennett Avenue and West 190th Street in Fort Tryon Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2019
Projected Completion Date: December 2020
Completion Date: March 2021

Procurement

Start Date: December 2020
Projected Completion Date: May 2021
Completion Date: October 2021

Construction

Start Date: August 2022
Projected Completion Date: November 2022
Completion Date: December 2022

Understand how we build parks.

Funding

Total Funding: $1,142,000
Funding Source: Mayoral

Location

Fort Tryon Park, Manhattan

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 11/22/2024