Fort Tryon Park Retaining Wall Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the retaining wall along Bennett Avenue and West 190th Street in Fort Tryon Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2019
Projected Completion Date:
December 2020
Completion Date:
March 2021
Procurement
Start Date: December 2020
Projected Completion Date:
May 2021
Completion
Date:
October 2021
Construction
Start Date: August 2022
Projected Completion Date:
November 2022
Completion Date: December 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Fort Tryon Park, Manhattan
Project Staff
Project Liaison: Contact Us
Contact NYC Parks
about this project