East River Esplanade East 76th Street Seawall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the seawall, fill sinkholes, and restore the walking surface along the East River Esplanade at East 76th Street.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2020
Projected Completion Date: July 2021
Completion Date: January 2021

Procurement

Start Date: December 2020
Projected Completion Date: May 2021
Completion Date: October 2020

Construction

Start Date: August 2020
Projected Completion Date: November 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $875,000
Funding Source: Mayoral

Location

East River Walk, Manhattan

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 01/17/2025