Fort Washington Park Retaining Wall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct a retaining wall along Henry Hudson Parkway near West 180th Street in Fort Washington Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2019
Projected Completion Date: December 2020
Completion Date: March 2021

Procurement

Start Date: December 2020
Projected Completion Date: May 2021
Completion Date: October 2021

Construction

Start Date: September 2022
Projected Completion Date: January 2023
Completion Date: December 2022

Understand how we build parks.

Funding

Total Funding: $1,243,000
Funding Source: Mayoral

Location

Fort Washington Park, Manhattan

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 11/22/2024