Metropolitan Recreation Center Sidewalk Vault Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the sidewalk vault at Metropolitan Recreation Center.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

NYC Parks has received budget approval and is finalizing the work order documentation.

Project Timeline

Design

Assigned & Start Date: December 2019
Projected Completion Date: December 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: May 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Metropolitan Recreation Center, Brooklyn

 