Emerald Playground Public Restroom Building Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roof of the public restroom building in Emerald Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2019
Projected Completion Date:
August 2020
Completion Date:
August 2021
Procurement
Start Date: March 2020
Projected Completion Date:
August 2020
Completion
Date:
June 2021
Construction
Start Date: February 2022
Projected Completion Date:
May 2022
Completion Date: March 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Emerald Playground, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024