Emerald Playground Public Restroom Building Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof of the public restroom building in Emerald Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: August 2021

Procurement

Start Date: March 2020
Projected Completion Date: August 2020
Completion Date: June 2021

Construction

Start Date: February 2022
Projected Completion Date: May 2022
Completion Date: March 2022

Understand how we build parks.

Funding

Total Funding: $142,000
Funding Source: Mayoral

Location

Emerald Playground, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024