Astoria Park Field House Restrooms Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restrooms in the field house at Astoria Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2019
Projected Completion Date:
August 2020
Completion Date:
March 2020
Procurement
Start Date: March 2020
Projected Completion Date:
August 2020
Completion
Date:
February 2021
Construction
Start Date: March 2021
Projected Completion Date:
December 2021
Completion Date: December 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Astoria Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024