Cunningham Park Redwood Playground Public Restroom Building Sewer Line Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the sewer line of the public restroom building in Redwood Playground in Cunningham Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2020
Projected Completion Date: June 2020
Completion Date: September 2020

Procurement

Start Date: March 2020
Projected Completion Date: August 2020
Completion Date: December 2020

Construction

Start Date: September 2021
Projected Completion Date: July 2022
Completion Date: November 2021

Understand how we build parks.

Funding

Total Funding: $350,000
Funding Source: Mayoral

Location

Cunningham Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024