Cunningham Park Redwood Playground Public Restroom Building Sewer Line Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the sewer line of the public restroom building in Redwood Playground in Cunningham Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2020
Projected Completion Date:
June 2020
Completion Date:
September 2020
Procurement
Start Date: March 2020
Projected Completion Date:
August 2020
Completion
Date:
December 2020
Construction
Start Date: September 2021
Projected Completion Date:
July 2022
Completion Date: November 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Cunningham Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project