Citywide Services Complex and Garage Gas Line Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the gas line to the Citywide Services Complex and Garage in Randall's Island Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2020
Projected Completion Date: June 2020
Completion Date: February 2022

Procurement

Start Date: March 2020
Projected Completion Date: August 2020
Completion Date: January 2022

Construction

Start Date: March 2024
Projected Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $340,000
Funding Source: Mayoral

Location

Randall's Island Park, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024