Citywide Services Complex and Garage Gas Line Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the gas line to the Citywide Services Complex and Garage in Randall's Island Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2020
Projected Completion Date:
June 2020
Completion Date:
February 2022
Procurement
Start Date: March 2020
Projected Completion Date:
August 2020
Completion
Date:
January 2022
Construction
Start Date: March 2024
Projected Completion Date:
September 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Randall's Island Park, Manhattan
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024