Mosholu Parkway WWI Monument Lighting System Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a lighting system for Mosholu Parkway WWI Monument.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2010
Projected Completion Date: January 2012
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date: October 2012
Completion Date: December 2012

Construction

Start Date: March 2013
Projected Completion Date: August 2013
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: $78,000
Funding Source: City Council

Location

Mosholu Parkway, Bronx
Mosholu Parkway at Marion & Hull Avenues
Community Board: 07, 08

 

Project Staff

Project Liaison: Katerine Borrome