Devoe Park Maintenance Shed Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the maintenance shed roof at Devoe Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2019
Projected Completion Date: June 2020
Completion Date: August 2021

Procurement

Start Date: March 2020
Projected Completion Date: August 2020
Completion Date: June 2021

Construction

Start Date: October 2021
Projected Completion Date: April 2022
Completion Date: December 2021

Understand how we build parks.

Funding

Total Funding: $74,000
Funding Source: Mayoral

Location

Devoe Park, Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024