Devoe Park Maintenance Shed Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the maintenance shed roof at Devoe Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2019
Projected Completion Date:
June 2020
Completion Date:
August 2021
Procurement
Start Date: March 2020
Projected Completion Date:
August 2020
Completion
Date:
June 2021
Construction
Start Date: October 2021
Projected Completion Date:
April 2022
Completion Date: December 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Devoe Park, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024