Silver Lake Park Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct paths and pavement in the southern half of Silver Lake Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2019
Projected Completion Date: June 2020
Completion Date: March 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Construction

Start Date: April 2021
Projected Completion Date: October 2021
Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $1,138,000
Funding Source: Mayoral

Location

Silver Lake Park, Staten Island

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024