Silver Lake Park Pavement Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct paths and pavement in the southern half of Silver Lake Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2019
Projected Completion Date:
June 2020
Completion Date:
March 2020
Procurement
Start Date: September 2019
Projected Completion Date:
February 2020
Completion
Date:
February 2020
Construction
Start Date: April 2021
Projected Completion Date:
October 2021
Completion Date: September 2021