Mt. Hope Garden Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the retaining walls and play areas at Mt. Hope Garden.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2014
Projected Completion Date: October 2015
Completion Date: July 2015

Procurement

Start Date: July 2015
Projected Completion Date: April 2016
Completion Date: September 2016

Construction

Start Date: February 2017
Projected Completion Date: February 2019
Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $4,570,000
Funding Sources:
  • City Council
  • Mayoral

Location

Mount Hope Garden, Bronx
West side of Creston Avenue between East Burnside Avenue East 179th Streets
Community Board: 05

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024