Dry Dock Pool Deck Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pool deck at Dry Dock Pool.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2019
Projected Completion Date: September 2020
Completion Date: September 2021

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: September 2021

Construction

Start Date: November 2021
Projected Completion Date: June 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $1,200,000
Funding Source: Mayoral

Location

Dry Dock Playground, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024