Corona Golf Playground Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavements at Corona Golf Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2019
Projected Completion Date: May 2020
Completion Date: March 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Construction

Start Date: March 2020
Projected Completion Date: July 2020
Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $350,000
Funding Source: City Council

Location

Corona Golf Playground, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024