Grand Playground Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct Grand Playground, including a new play area, sitting area, spray shower, and basketball court.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2011
Projected Completion Date: May 2014
Completion Date: April 2015

Procurement

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: May 2016

Construction

Start Date: May 2016
Projected Completion Date: August 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $2,349,000
Funding Source: City Council

Location

Grand Playground, Bronx
Grand Avenue and West 181st Street
Community Board: 05

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025