Sumner Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building in Sumner Playground.

Project Timeline

Design

Assigned & Start Date: August 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Construction

Start Date: March 2021
Projected Completion Date: December 2021
Completion Date: December 2021

Understand how we build parks.

Funding

Total Funding: $996,000
Funding Source: Mayoral