McKinley Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in McKinley Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2019
Projected Completion Date:
February 2020
Completion Date:
February 2020
Procurement
Start Date: September 2019
Projected Completion Date:
February 2020
Completion
Date:
February 2020
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: July 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
McKinley Playground, Manhattan
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024