McKinley Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building in McKinley Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $911,000
Funding Source: Mayoral

Location

McKinley Playground, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024