Design
Assigned & Start Date: April 2019
Projected Completion Date:
December 2019
Completion Date:
December 2019
Procurement
Start Date: July 2019
Projected Completion Date:
December 2019
Completion
Date:
November 2019
Construction
Start Date: March 2020
Projected Completion Date:
June 2020
Completion Date: September 2020