Shore Road Bicycle Path Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the hazardous and deteriorated section of the existing asphalt bicycle path between (approximately) Bay 8th and Bay 14th Street.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2019
Projected Completion Date:
December 2019
Completion Date:
November 2019
Procurement
Start Date: September 2019
Projected Completion Date:
February 2020
Completion
Date:
November 2019
Construction
Start Date: May 2020
Projected Completion Date:
December 2020
Completion Date: August 2020
Understand how we build parks.
Funding
Funding Source: City Council
Location
Belt Parkway/Shore Parkway, Brooklyn
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks