Highbridge Park Step Street Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will restore the step street and surrounding landscape in Highbridge Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2011
Projected Completion Date:
June 2015
Completion Date:
September 2018
Procurement
Start Date: September 2018
Projected Completion Date:
June 2019
Completion
Date:
January 2020
Construction
Start Date: March 2020
Projected Completion Date:
September 2021
Completion Date: October 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Federal
- Mayoral
Location
Highbridge Park, Bronx
West 170th Street between University Avenue and Sedgwick Avenue
Community Board: 04
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024