Bronx Park Anadromous Fish Passage Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will install a specially-built passage to help fish swim upstream. The passage will establish a sustainable herring population on the river by providing access to freshwater spawning habitat. The project will also include a canoe portage, reconstruction of parts of the dam, fencing, a new picnic area and restoration of the surrounding ecosystem.
Project Timeline
Design
Assigned & Start Date: April 2011
Projected Completion Date:
April 2012
Completion Date:
May 2012
Procurement
Start Date: May 2012
Projected Completion Date:
January 2013
Completion
Date:
January 2013
Construction
Start Date: April 2013
Projected Completion Date:
December 2014
Completion Date: December 2014
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
- Private
- State
Location
Bronx Park, Bronx
Bronx River at East 182nd Street
Community Board: 06, 07, 11, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025