  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the sidewalks, curbs, accessible ramps, and pipe rail fencing at Kolbert Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2019
Projected Completion Date: May 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: October 2019
Completion Date: July 2019

Construction

Start Date: November 2019
Projected Completion Date: May 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $364,000