Fort Totten Park Telecommunication Lines Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the telecommunication lines at Fort Totten Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2018
Projected Completion Date:
May 2019
Completion Date:
May 2019
Procurement
Start Date: January 2019
Projected Completion Date:
June 2019
Completion
Date:
April 2019
Construction
Start Date: May 2019
Projected Completion Date:
November 2019
Completion Date: August 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Fort Totten Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024