Ocean Breeze Park Maintenance Area Fencing Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct screen fencing around the garbage management system at Ocean Breeze Park to reduce the visual impact to the public.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2018
Projected Completion Date: April 2019
Completion Date: February 2019

Procurement

Start Date: January 2019
Projected Completion Date: June 2019
Completion Date: March 2019

Construction

Start Date: March 2019
Projected Completion Date: September 2019
Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $76,000
Funding Source: Mayoral

Location

Ocean Breeze Park, Staten Island

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024