Hamilton Fish Park Basketball Courts and Adult Fitness Equipment Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball courts and adult fitness equipment at Hamilton Fish Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2018
Projected Completion Date: October 2019
Completion Date: March 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Construction

Start Date: September 2020
Projected Completion Date: December 2020
Completion Date: May 2021

Understand how we build parks.

Funding

Total Funding: $638,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Hamilton Fish Park, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025