John Finley Walk 82nd Street ADA Ramp Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct a masonry ramp to provide ADA access to John Finley Walk at East 82nd Street.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2018
Projected Completion Date:
August 2019
Completion Date:
June 2019
Procurement
Start Date: October 2018
Projected Completion Date:
March 2019
Completion
Date:
May 2019
Construction
Start Date: January 2020
Projected Completion Date:
April 2020
Completion Date: March 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
East River Walk, Manhattan
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025